Minnetonka, MN

Stratasys

Project Summary

Scope: Construction, Prefabrication, Design/Assist

 

Features:

  • Large scale distribution of power with new install of three 2,000 AMP services
  • Connections to hundreds of pieces of industrial machinery
  • Multi-phase, multi-floor build out

 

Our Role:

During the remodel of Stratasys’ 181,000 SF, multi-floor building in Minnetonka, MN NEI Electric maintained a hands-on approach, ensuring the extensive power connections will reliably deliver. With a budget of $4.3M, this project required multiple phases over 14 months.

 

‍Project Highlight:

Our team optimized power distribution by installing and utilizing 3,000 ft of cable tray — largely customized and assembled in our prefabrication shop.